The project to install water and wastewater trunk lines along the Millennium Trail has been plagued by delays due to high ground water levels, buried steel railway lines and hard rock formations. (Jason Parks/Gazette Staff)
It’s more than a year late, and millions over budget, but the Wellington Trunk Water main and sanitary sewer project is nearing its final stages.
The County detailed recent works on October 23 and November 10. The contractor has made the final watermain connection and Consecon Street is now open to traffic. The final section of sewer forcemain across Consecon Street has been installed and testing confirms there are no issues with the installation of the new sanitary sewer.
Hydro One has installed new wiring and connected power for the new sewage pumping station. A yard hydrant has been installed at the end of West Street. Final testing of the new sewage pumping station components is ongoing.
With the project nearing completion, Kaitlin Corporation says it will begin construction on its Cork and Vine subdivision in spring 2027.
“It’s exciting that this enabling infrastructure appears to finally be almost be done!” said Kaitlin’s Devon Daniell in an email to the Gazette.
“Local servicing is hard to start over the winter, so our hope is to get that going in the spring. As for the actual homes, construction would follow on the heels of the local servicing, hopefully also in 2027,” confirmed Mr. Daniell.
All told, the project is expected to cost $31 million.
Originally, a tender contract was awarded for $16 million in 2023. A $6 million pumping station was added when it was discovered the sanitary sewer pipes couldn’t be buried deep enough to permit gravitational flow.
In June 2026, staff reported costs had ballooned to $31 million. Among other difficulties, including discovering steel railway lines deep under the trail that needed to be removed, huge amounts of groundwater flooded the project, creating a cascading series of problems, cost overruns, and construction delays. That the sheer volume of groundwater had not been detected in pre-engineering studies may have cost Project Engineer David MacPherson his job.
The staff report also notes, however, that approximately $29 million of the new total project costs of $31.1 million are considered development charge recoverable. “A significant portion of the future debt payments are expected to be supported through development charges collected…within the Wellington urban serviced area.”
There is still work to be done before municipal servicing can begin. Site grading and installation of fencing and bollards is now taking place at the sewage pumping station, as well as site restoration and paving.
Crews are still working through final testing and commissioning of the new sewage pumping station.
Commissioning is tentatively set for November 23, followed by 12 weeks of testing. The County will then take responsibility for the trunklines.